5/25- Williams Hall/ISB Construction Updates
	
 
  
    
  
          
            Work in progress:
	- Temporary steam condensate line in tunnel is complete along with taps on main condensate and steam feeds for future connections.
 
	- Chilled water line hangers are being installed above AHUs in Williams mechanical room.
 
	- Steel erection in sequence 4 & 5.
 
	- Steel detailing in sequence 2 & 3.
 
	- Metal floor decking has begun in sequence 1.
 
	- Form basement retaining wall between column line B & C.
 
	- Removal of windows from Williams Hall west side - window protection has been installed.
 
	- Abatement and demolition of instructional labs on the first floor south end has begun.
 
Looking forward:
	- Continue with steam and condensate line work in the tunnel.
 
	- Continue with the chilled water line extensions above the AHUs in the basement.
 
	- Continue steel erection in sequence 5 & 6.
 
	- Continue steel detailing in sequence 2 & 3.
 
	- Start metal decking in sequence 2.
 
	- Form elevator #2 pour #3.
 
	- Pour lift #3 at stair #3.
 
	- Start roof replacement on Williams Hall west side.
 
	- Continue with demolition of brick on west side of Williams Hall.
 
	- Continue with demolition and abatement on the 1st floor (south) of Williams Hall.
 
 
      
    
    
 
  POSTED: Wednesday, May 25, 2016 12:00 AM
 
    
        